Summary as of 31st July 2019

Sprint 38

Things to be aware of

  • The first establishment has been migrated to the new ASPEL system. Users at the establishment logged in today. No critical issues were reported.

Just Done

  • Release of new ASPEL system to first establishment users.

About to Do/Doing

  • Continued roll-out of new ASPEL system to two further establishments as part of initial cohort.

Click here for metrics / progress against plan

Sprint 38 - Week 2 - Release 1

Priority Bugs

Link to view of status of all currently open priority bugs

Risks

Links to Project Risks in Trello Link to Risk Chart

Note

The risk managment process will be reviewed after the release period

Sprint Planning

Our goals for the sprint are:

  • Ship it!

Google Analytics for this report

Google Analytics