Summary as of 28st August 2019
Sprint 40
Just Done
- Improvements to word document download
- Make comment boxes bigger when comment is being added
- Make RA conditions yes/no question on legacy and new ppls
- Allow for apostrophes to be used in email addresse
About to Do/Doing
- PPL Revocation
- Editing and resubmitting of tasks
- Improving withdrawal of tasks
Things to be aware of
- Rollout to all establishments has completed
Bugs Fixed this week
The following bugs were fixed this week.
Bug Fixes to week ending 28th August 2019
Support tickets and known issues
Click here for metrics / progress against plan
Week 2 - Sprint 39 - Release 1
We planned these issues in this sprint
Our goals for the sprint are:
- Edit and resubmit tasks
- Complete roll-out to establishments
- Support internal and external users