Summary as of Wednesday 28 April 2021

Sprint 83 (Pterodactyl)

A pterodactyl

Weekly summary

Email alerting for PPL expiry (at 12, 6, 3 and 0 months) went live this week. The team also continued to address issues arising from early use of inputting of RoPs.

Just Done

  • PPL expiry notifications
  • ASRU view of complete PIL data set for a user
  • Consolidated reporting for RoPs by establishment

About to Do/Doing

  • Assignment of tasks to ASRU users
  • Updates to PPL granting workflow
  • Overdue RoPs reporting

Bugs Fixed this week

The following bugs were fixed this week. Bug Fixes week to Wednesday 28 April 2021

We planned the following issues in this sprint Sprint 83

Support tickets and known issues

Link to Support Board

Support board - cached

Click here for metrics / progress against plan

Sprint 83

Post Release Roadmap

We planned this goal for the current sprint 83 (pterodactyl)

Initial release of changes to ASRU workflow - assignment of tasks, reviewing the granting process for each licence type (working software)

We planned this goal for the last sprint 82 (Ocelot)

Send expiry notifications for PPLs (working software) [Done]

Screenshot of recently developed software

An email alert for an expiring PPL