Summary as of Wednesday 27 November 2019

Sprint 47

Things to bear in mind

  • We will be migrating from the current instance of Jira our issue tracking tool to a new instance.
  • This may cause some disruption to issue tracking
  • We will only migrate attachments to issues for live issues

Just Done

  • Discard draft PIL - working software
  • transfer pils between establishment - working software
  • AWERB research
  • Test billing designs

About to Do/Doing

  • Test billing designs - user research
  • Grant new PEL - working software
  • Design digitise paper PPLs

Bugs Fixed this week

The following bugs were fixed this week. Bug Fixes week to Wednesday 27 November 2019

We planned the following issues in this sprint Sprint 47

Support tickets and known issues

Link to Support Board

Support board - cached

Click here for metrics / progress against plan

Sprint 47

Post Release Roadmap

Our goals for the previous sprint were:

  1. Design invoicing [Done]
  2. Research AWERBs [Done]
  3. Working software - transfer a PIL between establishments [Done]

Our goals for the current sprint are:

  1. Grant New PEL - working software
  2. Test billing wireframes
  3. Digitise paper PPLs - Design

Sample Design Prototypes