Summary as of 27th June 2018

Sprint 11

What’s Blocking us / Issues

We have added two potential risks to the risk register to be discussed at next meeting:

  • On the back of receiving Authority to Operate (ATO) we are sensitive that there might be issues regarding data quality which may need addressing
  • We have highlighted in retrospective the need to limit and control scope through user research/design and development

Just Done

  • Develop working software for add/remove room from external users
  • Design iterations of inbox and amendment journeys for all views
  • User research with inspectors for add a room as part of amending an establishment licence

About to Do/Doing

  • Development of working software for the “end to end” amendment journey
  • Incorporation of findings from user research with HOLCs and inspectors into designs
  • Iteration of designs for inboxes for inspectors and HOLCs

Things to be aware of

  • Tomorrow the team are running a combination “Show and Tell” and research event with 40+ HOLCs

Click here for our High-Level Road map

Link to Live Road map in Trello (Cached Image)

Click here for metrics / progress against plan

Week 1 - Sprint 11 - Release 1

Risks

Links to Project Risks in Trello (Cached Image)

Risk Management Chart

Sprint Planning

Our goals for the sprint are

  • Develop working software for add/remove room from external users
  • Design iterations of inbox and amendment journeys for all views
  • User research with inspectors for add a room as part of amending an establishment licence

Sample Design Prototype

  • Links to demonstrated working software:

Username: holc

Password: holc

HTML5 Icon

Username: inspector

Password: inspector

HTML5 Icon