Summary as of 26th February 2019
Sprint 27
Just Done
- Begun development of scenario and user research for legacy PIL amendment lifecycle
- Development of working software for PPL submission
About to Do/Doing
- Research with inspectors for reviewing, providing feedback and recommending a PPL application
- Designs (for PPL review) and feedback at the show and tell next week
- Email notifications for significant changes in workflow
- Creating user journeys to manage legacy PPLs
- Planning usability testing with licensing officers
Things to be aware of
- Project Governance Review is today in 2MS
- We intend to release a new maintenance release of the PPL drafting tool roughly once a week on a Monday. Detail of what will be in each release will be here https://ppl-prototype.herokuapp.com/changelog
Click here for Prioritised Road Map
Prioritised Road Map (Cached Image)
Click here for metrics / progress against plan
Week 2 - Sprint 27 - Release 1
Burnup Chart
Risks
Links to Project Risks in Trello
Link to Risk Chart
Sprint Planning
- We planned the following issues in sprint planning
Link to Issues in Jira (Cached Image)
Our goals for the sprint are:
- Project Application Submission
- Send notification emails
- Legacy PPL amendment lifecycle
- Test University of Croydon with Licensing Officers
- Design granting PPL (standard conditions, etc)
Screenshots of the PPL application prototype