Summary as of 24th April 2019

Sprint 31 - Mid-Sprint

Just Done

  • Proof of concept for NTS export
  • Status banners for Non Active Licences
  • Design - highlight changes in PPLs for amendments

About to Do/Doing

  • Design - updates to activity logs
  • Plan PPL layout testing with inspectors (legacy and new)
  • Print view of protocols for new licence
  • Per question commentiong on PPL applications

Things to be aware of

  • This week is a short week - missing Good Friday and Easter Monday

Click here for Prioritised Road Map

Prioritised Road Map (Cached Image)

Click here for metrics / progress against plan

Week 2 - Sprint 31 - Release 1

Burnup Chart

Burnup Chart

Risks

Links to Project Risks in Trello Link to Risk Chart

Sprint Planning

Our goals for the sprint are:

  1. Content design for PPL applications
  2. Per question commenting on PPL applications and amendments

Screenshots

Print format views of granted legacy PPL licences

HTML5 Icon
HTML5 Icon