Summary as of 23 September 2020

Sprint 67

Just Done

  • Prototyped a restructured NTS within the PPL application and updated PPL overview page layout - design
  • Held three research sessions with HOLCs and PPL holders testing the NTS restructure in the PPL application - user research
  • Held a RoPs research session with a HOLC from a contract research organisation exploring returns for service licences - user research
  • Scheduled four more research sessions for RoPs with HOLCs and PPL holders - user research
  • Fixed issue with missing PIL numbers - working software

About to Do/Doing

  • Iterate the PPL assessments designs - design
  • Holding three sessions on NTS restructure in the PPL application - user research
  • Holding three sessions on RoPs - user research
  • PIL E - working software
  • Support adding mitigations to statutory deadlines that have expired - working software

Bugs Fixed this week

The following bugs were fixed this week. Bug Fixes week to 23 September 2020

We planned the following issues in this sprint Sprint 67

Support tickets and known issues

Link to Support Board

Support board - cached

Click here for metrics / progress against plan

Sprint 67

Post Release Roadmap

Goals for current sprint

  1. Cat E PIL release candidate - working software
  2. Iterate PPL assesments - design
  3. Complete research on NTS changes to PPL applications - user research

Sample Design Prototypes

HTML5 Icon