Summary as of 23 September 2020
Sprint 67
Just Done
- Prototyped a restructured NTS within the PPL application and updated PPL overview page layout - design
- Held three research sessions with HOLCs and PPL holders testing the NTS restructure in the PPL application - user research
- Held a RoPs research session with a HOLC from a contract research organisation exploring returns for service licences - user research
- Scheduled four more research sessions for RoPs with HOLCs and PPL holders - user research
- Fixed issue with missing PIL numbers - working software
About to Do/Doing
- Iterate the PPL assessments designs - design
- Holding three sessions on NTS restructure in the PPL application - user research
- Holding three sessions on RoPs - user research
- PIL E - working software
- Support adding mitigations to statutory deadlines that have expired - working software
Bugs Fixed this week
The following bugs were fixed this week. Bug Fixes week to 23 September 2020
We planned the following issues in this sprint Sprint 67
Support tickets and known issues
Click here for metrics / progress against plan
Goals for current sprint
- Cat E PIL release candidate - working software
- Iterate PPL assesments - design
- Complete research on NTS changes to PPL applications - user research