Summary as of 22nd August 2018

What’s Blocking us / Issues

  • We are still waiting for security clearance and access passes for Lunar house for two members of the team

Just Done

  • Demonstrated in Show and Tell - end-to-end user on boarding
  • Demonstrated the prototypes for PIL application which were used in User Research
  • Conducted User Research with HOLCs, NTCOs and PILhs at a large academic establishment

About to Do/Doing

  • Profiles: Add Non-PIL Details to Profile 1st Design
  • Kick off PPL meeting with inspectors
  • Implement external permission model as working software

Click here for our High-Level Road map

Link to Live Road map in Trello (Cached Image)

Click here for metrics / progress against plan

Week 1 - Sprint 15 - Release 1

Burnup Chart

Burnup Chart

Risks

Links to Project Risks in Trello (Cached Image)

Risk Management Chart

Sprint Planning

Our goals for the sprint are:

  • Iterate PIL application prototype based on user-research feedback
  • Implement the HO design system in our production code
  • Implement permissions in UI

Sample Design Prototype