Summary as of 22nd August 2018
What’s Blocking us / Issues
- We are still waiting for security clearance and access passes for Lunar house for two members of the team
Just Done
- Demonstrated in Show and Tell - end-to-end user on boarding
- Demonstrated the prototypes for PIL application which were used in User Research
- Conducted User Research with HOLCs, NTCOs and PILhs at a large academic establishment
About to Do/Doing
- Profiles: Add Non-PIL Details to Profile 1st Design
- Kick off PPL meeting with inspectors
- Implement external permission model as working software
Click here for our High-Level Road map
Link to Live Road map in Trello (Cached Image)
Click here for metrics / progress against plan
Week 1 - Sprint 15 - Release 1
Burnup Chart
Risks
Links to Project Risks in Trello (Cached Image)
Sprint Planning
- We planned the following issues in sprint planning today Link to Issues in Jira (Cached Image)
Our goals for the sprint are:
- Iterate PIL application prototype based on user-research feedback
- Implement the HO design system in our production code
- Implement permissions in UI
Sample Design Prototype
Log in with username/password holc/holc to view the most recent prototype