Summary as of 22nd May 2019
Sprint 33
Just Done
- Amend PIL - working software
- Add “other legal text”
- Tested working software with “Halloween data” with establishment users
- Print view of the New granted licence
- Digital view of the New granted licence
- Project landing page for views of granted licence
About to Do/Doing
- Testing working software with Inspectors at ASRU conference
- Fix breadcrumb issues
- Testing the digital and print views of the granted licence with establishment users and inspectors
Things to be aware of
- The IT Health check is currently in progress
Click here for Roadmap
Click here for metrics / progress against plan
Week 1 - Sprint 33 - Release 1
Burnup Chart
Risks
Links to Project Risks in Trello Link to Risk Chart
Sprint Planning
- We planned the following issues in sprint planning Link to Issues in Jira (Cached Image)
Our goals for the sprint are:
- Test views of granted PPL
- Test Non-UGC at ASRU conference
- Working software PIL amendments
- Design PIL and PEL conditions and authorisations
- Design views of granted licence