Summary as of 22nd May 2019

Sprint 33

Just Done

  • Amend PIL - working software
  • Add “other legal text”
  • Tested working software with “Halloween data” with establishment users
  • Print view of the New granted licence
  • Digital view of the New granted licence
  • Project landing page for views of granted licence

About to Do/Doing

  • Testing working software with Inspectors at ASRU conference
  • Fix breadcrumb issues
  • Testing the digital and print views of the granted licence with establishment users and inspectors

Things to be aware of

  • The IT Health check is currently in progress

Click here for Roadmap

Roadmap

Click here for metrics / progress against plan

Week 1 - Sprint 33 - Release 1

Burnup Chart

Burnup Chart

Risks

Links to Project Risks in Trello Link to Risk Chart

Sprint Planning

Our goals for the sprint are:

  1. Test views of granted PPL
  2. Test Non-UGC at ASRU conference
  3. Working software PIL amendments
  4. Design PIL and PEL conditions and authorisations
  5. Design views of granted licence

Screenshots working software

HTML5 Icon
HTML5 Icon

Google Analytics for this report

Google Analytics