Summary as of Wednesday 21 April 2021
Sprint 82 (Ocelot)
Weekly summary
This is our first week working while our product manager is away. We’re continuing to work on Returns of Procedures and making some more changes to retrospective assessments. The goal for this sprint - send expiry notifications for PPLs - is just about to be released.
Just Done
- Add automated email notifications for PPL expiry - working software
- Iterate on field mappings for ROPs data export to facilitate better consumption by the stats team - working software
- Add additional outputs to ROPs summary page - working software
- Fix issue with protocols being incorrectly marked as changed in certain PPL amendment circumstances - working software
About to Do/Doing
- Add basic view of historical PIL data
- ROPs numbers segmented by establishment
Bugs Fixed this week
The following bugs were fixed this week. Bug Fixes week to Wednesday 21 April 2021
We planned the following issues in this sprint Sprint 82
Support tickets and known issues
Click here for metrics / progress against plan
Roadmap Visualisaton (Experimental)
The goal for the current sprint (Ocelot) is:
Send expiry notifications for PPLs (working software) Ocelot