Summary as of Wednesday 21 April 2021

Sprint 82 (Ocelot)

Ocelot

Weekly summary

This is our first week working while our product manager is away. We’re continuing to work on Returns of Procedures and making some more changes to retrospective assessments. The goal for this sprint - send expiry notifications for PPLs - is just about to be released.

Just Done

  • Add automated email notifications for PPL expiry - working software
  • Iterate on field mappings for ROPs data export to facilitate better consumption by the stats team - working software
  • Add additional outputs to ROPs summary page - working software
  • Fix issue with protocols being incorrectly marked as changed in certain PPL amendment circumstances - working software

About to Do/Doing

  • Add basic view of historical PIL data
  • ROPs numbers segmented by establishment

Bugs Fixed this week

The following bugs were fixed this week. Bug Fixes week to Wednesday 21 April 2021

We planned the following issues in this sprint Sprint 82

Support tickets and known issues

Link to Support Board

Support board - cached

Click here for metrics / progress against plan

Sprint 82

Post Release Roadmap

Roadmap Visualisaton (Experimental)

The goal for the current sprint (Ocelot) is:

Send expiry notifications for PPLs (working software) Ocelot

Screenshots of new working software

Open and close all the sections of a protocol from either the top or bottom

HTML5 Icon
HTML5 Icon