Summary as of 21st February 2018

What is Blocking Us / Issues

  • Lack of access to Lunar House because of some members of the team are waiting for security clearance is still an impediment. This has been addressed by the acquisition of temporary accommodation in Landsdowne Road - just a few minutes from Lunar House.

Just Done

  • Created design prototypes to be tested with selected users next week
  • Data schema for establishment licences
  • Drafted data migration plan
  • Created proof of concept migration tools to migrate data exports from ASPeL into our databases
  • Survey has been sent out to Establishments to provide baseline KPIs - so far 26% percent of establishments have responded
  • Piloted successfully remote testing via Skype with a HOLC from commercial organisation

About to Do/Doing

  • Testing our prototypes with a HOLC from a university and a commercial organisation in two separate sessions tomorrow
  • More research with selected participants will take place next week
  • Work will continue to build out our data migration prototype
  • We will carry out further research to understand establishment roles and their relationship to training and personal licences
  • Looking to grow the team

Things to be aware of

  • This is week 8 that the team has been working together

Click here for our High-Level Roadmap

Link to Live Roadmap in Trello (Cached Image)

Click here for metrics / progress against plan

Week 1 - Sprint 2 - Release 1

Link to Issues in Jira

Risks

Links to Project Risks in Trello (Cached Image)

Risk Management Chart

Sprint Planning

  • We planned the following issues in sprint planning Link to Issues in Jira (Cached Image)
  • Our two goals for the sprint are
    1. “Build out data migration”
    2. “Test View Establishment Licence with Users”

Prototype

  • Log in to this technical prototype with username “holc” and password “holc” to see Mock data objects loaded into our database and served with our API for the “University of Croydon”