Summary as of Wednesday 20 July 2022

Sprint 114 (Umbrella bird)

By Hectonichus - Own work, CC BY-SA 3.0, https://commons.wikimedia.org/w/index.php?curid=22003026

Just Done

  • Designs for suspending licences (pending confirmation from ASRU on banner wording)
  • Migrate to new infrastructure for storing images in PPLs
  • Write migration script for existing images in PPLs
  • Add reminders for upcoming ROPs submissions - working software
  • Add reminders for licence conditions with deadlines - working software

About to Do/Doing

  • Writing up developer specifications for suspending licences and reusable steps - design
  • Reject a PPL - working software
  • Change process for marking a PPL application as complete and correct - working software
  • Migrate existing PPL versions with images to new infrastructure - working software

Bugs Fixed this week

The following bugs were fixed this week. Bug Fixes week to Wednesday 20 July 2022

We planned the following issues in this sprint Sprint 114

Support tickets and known issues

Link to Support Board

Support board - cached

Click here for metrics / progress against plan

Sprint 114

Post Release Roadmap

We set these areas of focus for this sprint

  1. Release refuse a PPL - working software
  2. Design specifications for reusable steps
  3. HOCS Audit

These were the areas of focus for the previous sprint

  1. Designs for suspend a licence [Done]
  2. Release time based conditions [In progress]
  3. Migrate images out of PPL versions [In progress]

Sample Design Prototypes

Example ‘suspended PIL’ banner (final wording to be confirmed by ASRU)

HTML5 Icon