Summary as of Wednesday 20 July 2022
Sprint 114 (Umbrella bird)
Just Done
- Designs for suspending licences (pending confirmation from ASRU on banner wording)
- Migrate to new infrastructure for storing images in PPLs
- Write migration script for existing images in PPLs
- Add reminders for upcoming ROPs submissions - working software
- Add reminders for licence conditions with deadlines - working software
About to Do/Doing
- Writing up developer specifications for suspending licences and reusable steps - design
- Reject a PPL - working software
- Change process for marking a PPL application as complete and correct - working software
- Migrate existing PPL versions with images to new infrastructure - working software
Bugs Fixed this week
The following bugs were fixed this week. Bug Fixes week to Wednesday 20 July 2022
We planned the following issues in this sprint Sprint 114
Support tickets and known issues
Click here for metrics / progress against plan
We set these areas of focus for this sprint
- Release refuse a PPL - working software
- Design specifications for reusable steps
- HOCS Audit
These were the areas of focus for the previous sprint
- Designs for suspend a licence [Done]
- Release time based conditions [In progress]
- Migrate images out of PPL versions [In progress]