Summary as of 20th June 2018
What’s Blocking us / Issues
- Data migration continues to be the biggest issue affecting the project but this is being addressed through a process of application for authority to operate (ATO)
Just Done
- Submitted application for authority to operate (ATO)
- Conducted User Experience “surgery” for inbox design (inspectors) and amendments journey
- Preparations for the meeting with establishment users at the end of the month
About to Do/Doing
- Run large showcase of existing software, designs and conduct research sessions with up to 40 establishment users
- User research with inspectors: inspectors’ recommendations for PEL amendments and inspector’s inbox
- Develop working software for “add a room” and “remove a room” from the schedule of premises on the establishment licence
Things to be aware of
- The team have received the output from the Alpha service assessment - the feedback is that we have met the requirements for Alpha
Click here for our High-Level Road map
Link to Live Road map in Trello (Cached Image)
Click here for metrics / progress against plan
Week 2 - Sprint 10 - Release 1
Risks
Links to Project Risks in Trello (Cached Image)
Sprint Planning
- We planned the following issues in sprint planning today Link to Issues in Jira (Cached Image)
Our Goals for the Sprint are:
- Develop working software for add/remove room from external users
- Design iterations of inbox and amendment journeys for all views
- User research with inspectors for add a room as part of amending an establishment licence
- Prepare for meeting with establishment users on 28th June