Summary as of 19th June 2019
Sprint 35
Just Done
- Allow tables to be entered in the rich text editor - working software
- End to end testing with “Halloween data” with establishments, licensing and inspectors
- Added issues arising from end to end testing to product backlog
- Capturing animal types for PIL applications
- New designer onboarding
- Digital view of the new granted licence - design
- PPL Holder amendment - Establishment view - design
About to Do/Doing
- Change PPL holder - working software
- Planning for Inspector Roadshow
- Changes to design of view of granted PPL license.
- PPL Holder amendment - ASRU reviews
Things to be aware of
- Today we will take another copy of the live data AKA “Guatamalan Father’s Day” data.
Click here for Prioritised Road Map
Click here for metrics / progress against plan
Sprint 35 - Week 1 - Release 1
Burnup Chart
Risks
Links to Project Risks in Trello Link to Risk Chart
Sprint Planning
- We planned the following issues in sprint planning Link to Issues in Jira (Cached Image)
Our goals for the sprint are:
- Amend PPL holder - dev
- Amend establishment details - dev
- Plan and conduct ASRU roadshow
- Design views of granted PPL licences (digital, print, new, legacy)
Screenshots
What can I do?
- Video of PIL application