Summary as of Wednesday 19 January 2022
Sprint 101 (Hare)
Just Done
- Plan testing of compliance flags designs with inspectors and enforcement team - user research
- Initial designs for the compliance flags journey - design
- Improve messaging for submitted nil return for ROPs - working software
- Update filter labels in task search - working software
- Downloadable monthly report for tasks completed by type and meeting internal SLAs - working software
About to Do/Doing
- Test enforcement flags with users round 2 - user research
- Schedule sessions for compliance flags testing round 2 - user research
- Writing up performance metrics and task deadline designs for development, next iteration of designs for compliance flags - design
- Include task list filters for PELs - working software
- Include licence number in revealing section of task search - working software
- Investigate slow loading of setup pages for ROPs - working software
Bugs Fixed this week
The following bugs were fixed this week. Bug Fixes week to Wednesday 19 January 2022
We planned the following issues in this sprint Sprint 101
Support tickets and known issues
Click here for metrics / progress against plan
We set the following goals for this sprint
- Plan testing of enforcement flags - round 2 (User research)
- Displaying deadlines on tasks (working software)
- Preparing enforcement flags for testing - round 2 (design)
These were the goals for the previous sprint
- Initial designs for compliance - design flags [Done]
- Internal target reporting - working software [In progress]
- Schedule sessions for compliance flags designs - user research [Done]