Summary as of 17th July 2019
Sprint 37 - mid-sprint
What’s Blocking us / Issues
- We are still working to get ATO (authority to operate)
Just Done
- Discard project versions
- Licence number generator
- Accessibility audit
About to Do/Doing
- ASRU user can update PEL
- ASRU user can modify ASRU permissions
- .ppl file upload
Click here for metrics / progress against plan
Release Roadmap
Countdown to release: critical and major bugs
This image shows all the issues that need to be addressed before the first release.
Outstanding Critical and Major Bugs
Risks
Links to Project Risks in Trello Link to Risk Chart
Sprint Planning
- We planned the following issues in sprint planning Link to Issues in Jira (Cached Image)
Our goals for the sprint are:
- ATO
- Digital and Print view for new and legacy licences - working software
- Declarations review
- Decide release schedule
- High level plan for Beta service assessment
- Cat E Pils - Design