Summary as of Wednesday 17 February 2021

Sprint 78 (Komodo Dragon)

HTML5 Icon

Things to be aware of

  • Our product manager will gradually move off the project in the coming months. A replacement will be recruited and a slow and careful handover will take place.

Just Done

  • RoPs summary of findings - user research
  • RoP research analysis - design
  • Submit a return of procedures - working software
  • ASRU can now view a list of all completed tasks by type (e.g. all PIL applications) linked from the performance metrics - working software
  • Added hint text to application PDF - working software
  • CSV download for operational newsletter subscribers - working software
  • Added ability to view lists of completed tasks by type and filtered to date ranges and establishments - working software
  • Database design and initial UI work for RoP submission - working software
  • Fixed issue with transferring PPLs with additional availability between establishments - working software

About to Do/Doing

  • Animals in Science case study for HO DDaT use - user research
  • Planning user research for PPL rejection journey - user research
  • Developing specifications for building RoPs - design
  • Show correct licence holder on historic licence versions (i.e. pre-licence-holder change) - working software
  • Submit a RoP - working software
  • Improvements to display of comments and changes on PPLs which have been returned to the applicant at the initial endorsement stage - working software
  • Continuing development on RoP submission - working software

    Bugs Fixed this week

    The following bugs were fixed this week. Bug Fixes week to Wednesday 17 February 2021

We planned the following issues in this sprint Sprint 78

Support tickets and known issues

Link to Support Board

Support board - cached

Click here for metrics / progress against plan

Sprint 78

Post Release Roadmap

We set the following goals for this sprint (78, Komodo Dragon):

  1. RoP - create a return of procedures - working software
  2. Understand user needs for ppl rejection - user research

The goals for the previous sprint (77, Jaguar) were:

  1. Summarise the findings from RoPs testing with external users - agree improvements [Done]
  2. Performance metrics filtered task lists - working software - [Done]
  3. Delivery plan for RoPs [In Progress]

Sample Design Prototypes

HTML5 Icon

Google Analytics for this report

Google Analytics