Summary as of Wednesday 16 March 2022

Sprint 105 (Llama)

Ralf Roletschek, GFDL 1.2 <http://www.gnu.org/licenses/old-licenses/fdl-1.2.html>, via Wikimedia Commons

Just Done

  • Initial designs for allowing ASRU to mark applications as not ‘complete and correct’ - design
  • New metrics and reporting pages - working software
  • Fix issue with task search pages not loading for internal users - working software

About to Do/Doing

  • Updates to the “refuse a PPL” journey - design
  • Time based conditions - design
  • Building interfaces and data stores for non-compliance case functionality
  • Fix issue with removed named people still showing on schedule of premises
  • Handover documentation - service handover

We planned the following issues in this sprint

Sprint 105

Support tickets and known issues

Link to Support Board

Support board - cached

Click here for metrics / progress against plan

Sprint 105

Post Release Roadmap

We set the following goals for this sprint

  1. Enforcement flags - release candidate - working software
  2. Time-based conditions - design

These were the goals for the previous sprint

  1. Release candidate for new metrics pages [Done]
  2. Designs for changes to complete and correct functionality [Done]

Sample Design Prototypes

Initial designs for allowing ASRU to mark applications as not ‘complete and correct’