Summary as of 16th January 2019
Sprint 24 - Mid-Sprint
Just Done
- Manage named people
- Manage ASRU permissions
- Add further PPL prototype sections
- Add Rich Text Editor - inline images
About to Do/Doing
- Manage Named People
- NTCO approvals in PIL applications.
- Add further PPL prototype sections
- Add Rich Text Editor - inline images
- Designing PPL submission process
- Designing non-author view of PPL
- We are preparing to test the protocols with external users
- We are preparing to test the questions for other types of licences with contract research organisations (CROs)
Click here for Prioritised Road Map
Prioritised Road Map (Cached Image)
Click here for metrics / progress against plan
Week 1 - Sprint 24 - Release 1
Burnup Chart
Risks
Links to Project Risks in Trello
Sprint Planning
- We planned the following issues in sprint planning today Link to Issues in Jira (Cached Image)
Our goals for the sprint are:
- Design for viewing and reviewing PPL
- Design PPL Validation Rules
- Test Content for PPL
- PPL Draft Tool - Release Candidate Zero
- Create Amend Destroy any User Role
Screenshots of the PPL application prototype
Google Analytics for this report
This shows:
- total number of users
- number of new users