Summary as of 13th June 2018

What’s Blocking us / Issues

  • Access to data continues to be the biggest issue. We are working to gain authority to operate with the data, which is the next step in the process.

Just Done

  • Tested amendment prototype with 7 users from 6 external establishments
  • Completed “A Day in the life of a licensing officer”
  • Delivered amendment journey, first pass as working software for establishment users
  • Delivered projects list view for both internal an external users
  • Designed prototype amendment and inbox for testing with external users

About to Do/Doing

  • Further user research with inspectors
  • Design inbox and update amendments journeys (all views)
  • Develop working software for changing the details of a room and removing a room from licensed premises

Things to be aware of

  • We have a meeting with around 40 establishment users/administrators on June 28th

Click here for our High-Level Road map

Link to Live Road map in Trello (Cached Image)

Click here for metrics / progress against plan

Week 1 - Sprint 10 - Release 1

Risks

Links to Project Risks in Trello (Cached Image)

Risk Management Chart

Sprint Planning

Our Goals for the Sprint are:

  • Develop working software for add/remove room from external users
  • Design iterations of inbox and amendment journeys for all views
  • User research with inspectors for add a room as part of amending an establishment licence
  • Prepare for meeting with establishment users on 28th June

Sample Design Prototype

  • Links to demonstrated working software:

Username: holc

Password: holc

HTML5 Icon

Username: inspector

Password: inspector

HTML5 Icon