Summary as of Wednesday 13 May 2020

Sprint 58

Just Done

  • Added support for multiple NACWO assignments to approved areas - working software
  • Table of adverse effects PDF download - working software
  • Protocol summary table online view - working software
  • Showing remaining users in a role on a remove named role task - design
  • Iteration of training and exemptions improvements - design
  • Iteration of Cat E PIL - design
  • Completed PIL E user research

About to Do/Doing

  • Allow assignment of NVSs to approved areas - working software
  • PPL application PDF download - working software
  • Further iteration of Category E PIL designs based on research findings
  • Arrange and complete training profile user research

Bugs Fixed this week

The following bugs were fixed this week. Bug Fixes week to Wednesday 13 May 2020

We planned the following issues in this sprint Sprint 58

Support tickets and known issues

Link to Support Board

Support board - cached

Click here for metrics / progress against plan

Sprint 58

Post Release Roadmap

Our goals for the previous sprint were:

  1. Multiple people on SOP [In progress]
  2. Design Adding training modules to people’s profiles [Done]
  3. User Research complete PIL E research [Done]

Our goals for the current sprint are:

  1. Conduct training profile user research
  2. Design - Cat E applications for existing PIL holders
  3. Development - PPL application download as pdf