Just Done
- Added support for multiple NACWO assignments to approved areas - working software
- Table of adverse effects PDF download - working software
- Protocol summary table online view - working software
- Showing remaining users in a role on a remove named role task - design
- Iteration of training and exemptions improvements - design
- Iteration of Cat E PIL - design
- Completed PIL E user research
About to Do/Doing
- Allow assignment of NVSs to approved areas - working software
- PPL application PDF download - working software
- Further iteration of Category E PIL designs based on research findings
- Arrange and complete training profile user research
Bugs Fixed this week
The following bugs were fixed this week. Bug Fixes week to Wednesday 13 May 2020
We planned the following issues in this sprint Sprint 58
Support tickets and known issues
Click here for metrics / progress against plan
Our goals for the previous sprint were:
- Multiple people on SOP [In progress]
- Design Adding training modules to people’s profiles [Done]
- User Research complete PIL E research [Done]
Our goals for the current sprint are:
- Conduct training profile user research
- Design - Cat E applications for existing PIL holders