Summary as of 13th March 2019

Just Done

  • Tested working software with licensing officers
  • Notification by email - first working software
  • Data migration
  • Refactor of protocols in PPL application

About to Do/Doing

  • Planning research with establishments to explore the view of the granted licence
  • Activity log pages
  • Commenting and feedback
  • Continuing with data migration

Things to be aware of

  • A risk workshop has been arranged with security assurance colleagues

Click here for Prioritised Road Map

Prioritised Road Map (Cached Image)

Click here for metrics / progress against plan

Week 2 - Sprint 28 - Release 1

Burnup Chart

Burnup Chart

Risks

Links to Project Risks in Trello Link to Risk Chart

Sprint Planning

Our goals for the sprint are:

  1. Data Migration
  2. Legacy PPLs Skeleton Design
  3. Granting PPLs - design
  4. Split PPL Review into separate Chunks
  5. Licensing Officer - test working software
  6. Plan research view of licence

Screenshots of the PPL application prototype

HTML5 Icon
HTML5 Icon

Google Analytics for this report

This shows:

  • total number of users
  • number of new users

Google Analytics