Summary as of 13th March 2019
Just Done
- Tested working software with licensing officers
- Notification by email - first working software
- Data migration
- Refactor of protocols in PPL application
About to Do/Doing
- Planning research with establishments to explore the view of the granted licence
- Activity log pages
- Commenting and feedback
- Continuing with data migration
Things to be aware of
- A risk workshop has been arranged with security assurance colleagues
Click here for Prioritised Road Map
Prioritised Road Map (Cached Image)
Click here for metrics / progress against plan
Week 2 - Sprint 28 - Release 1
Burnup Chart
Risks
Links to Project Risks in Trello Link to Risk Chart
Sprint Planning
- We planned the following issues in sprint planning today Link to Issues in Jira (Cached Image)
Our goals for the sprint are:
- Data Migration
- Legacy PPLs Skeleton Design
- Granting PPLs - design
- Split PPL Review into separate Chunks
- Licensing Officer - test working software
- Plan research view of licence