Summary as of Wednesday 13 January 2021

Sprint 75 🦛

Just Done

  • Completed RoPs testing with internal users - user research
  • Completed data analysis - user research
  • Initial designs for indicating to users at additional availability establishments as to why certain features on PPLs aren’t available
  • Content for automated email notifications for projects due to expire - content design
  • Fixed issue with incorrect status showing on old revoked PPLs - working software
  • Fixed incorrect revocation dates on some old PPLs - working software

About to Do/Doing

  • Summarising findings from the last round of research with internal users - user research
  • Scheduling sessions for the second round of RoPs testing with external users - user research
  • Preparing the discussion guide for testing with external users - user research
  • Iterating the RoPs prototype to explore users editing and changing their RoP - design
  • Create internal user feedback survey on ASPeL/RoPs for ASRU users - content design
  • Build UI for full-content project search - working software

Note: A “discussion guide” is the collection of questions that we will ask during user research.

Bugs Fixed this week

The following bugs were fixed this week. Bug Fixes week to Wednesday 13 January 2021

We planned the following issues in this sprint Sprint 75

Support tickets and known issues

Link to Support Board

Support board - cached

Click here for metrics / progress against plan

Sprint 75

Post Release Roadmap

Roadmap Visualisaton (Experimental)

We planned these goals in the current sprint 🦛

  1. Complete RoPs testing with internal users - user research
  2. RA release candidate - working software

Google Analytics for this report