Summary as of 11th April 2018
What’s Blocking us / Issues
- Two further new-joining members of the team are currently waiting for SC clearance, problems with incorrect DOB for one team member have been solved
Just Done
- Make the download to PDF prototype a reusable component
- User research with 2 inspectors as part of constructing “A day in the life of an Inspector”
About to Do/Doing
- Download data to csv (comma-separated value) file
- User research with further inspectors and licensing team
- Development of service map for use in the Alpha service review and as a guide to ongoing development
Things to be aware of
- We are in the middle of a sprint
- This is the first sprint in which we explore the ASRU view of the establishment licence
Click here for our High-Level Road map
Link to Live Road map in Trello (Cached Image)
Click here for metrics / progress against plan
Risks
Links to Project Risks in Trello (Cached Image)
Sprint Planning
- We planned the following issues in sprint planning today Link to Issues in Jira (Cached Image)
Our three goals for the sprint are:
- Deploy existing software to pre-production environments
- Explore the end to end service using service mapping
- Explore the ASRU View of Establishment data
Prototypes
Prototypes for the ASRU view of establishment licences are about to tested with users.