Summary as of 11th April 2018

What’s Blocking us / Issues

  • Two further new-joining members of the team are currently waiting for SC clearance, problems with incorrect DOB for one team member have been solved

Just Done

  • Make the download to PDF prototype a reusable component
  • User research with 2 inspectors as part of constructing “A day in the life of an Inspector”

About to Do/Doing

  • Download data to csv (comma-separated value) file
  • User research with further inspectors and licensing team
  • Development of service map for use in the Alpha service review and as a guide to ongoing development

Things to be aware of

  • We are in the middle of a sprint
  • This is the first sprint in which we explore the ASRU view of the establishment licence

Click here for our High-Level Road map

Link to Live Road map in Trello (Cached Image)

Click here for metrics / progress against plan

Week 2 - Sprint 5 - Release 1

Risks

Links to Project Risks in Trello (Cached Image)

Risk Management Chart

Sprint Planning

Our three goals for the sprint are:

  • Deploy existing software to pre-production environments
  • Explore the end to end service using service mapping
  • Explore the ASRU View of Establishment data

Prototypes

Prototypes for the ASRU view of establishment licences are about to tested with users.