Summary as of Wednesday 10 June 2020
Sprint 60
Just Done
- Related tasks view on all licences/profiles - working sofware
- PPL authorisation and condition report - working software
- Fix issue with closed tasks not showing correct “before” values - note: this fix does not apply retrospectively to previously closed tasks
- Update handling of statutory deadlines - design
- Move users training and exemptions to their profile for use on both PPL and PIL applications - design
- Content design for generic success messages
- Research on training profiles has been completed with establishment users, inspectors and licensing officers
About to Do/Doing
- Reporting - PPL statutory deadline, RA reporting, PIL reporting
- ASRU profiles - working software
- Creating a landing page for each approved area - working software
- Improvements to task history - design
- Content iterations for PIL E journey
- Recruitment for Cat E PIL user research
Bugs Fixed this week
The following bugs were fixed this week. Bug Fixes week to Wednesday 10 June 2020
We planned the following issues in this sprint Sprint 60
Support tickets and known issues
Click here for metrics / progress against plan
These are the goals for the current sprint:
- Complete the research on Cat E PILs
- Design - improve task history
- Content design - complete content for PIL-E
- Working software - reporting RA, PPL SLAs and PILs
These were the goals for the previous sprint:
- Working software - show tasks related to a licence [Done]
- Design - manage statutory PPL deadlines [Done]
- Content - review success messages [Done]
- User Research Cat-E with existing PIL holders [Done]