Summary as of 10th April 2019
Just Done
- Working Software - PPL Inspector views submitted draft PPL from task review screen
- User Research - consolidated research findings for conditions and authorisations
- the team presented to 65 HOLCs at the HOLTIF meeting on the 8th of April
- we explored requirements for other types of PPL (excluding training)
About to Do/Doing
- “My tasks” list - working software
- Legact PPL - PDF export of protocols
- Content design digital view of granted project licence
Things to be aware of
Click here for Prioritised Road Map
Prioritised Road Map (Cached Image)
Click here for metrics / progress against plan
Week 2 - Sprint 30 - Release 1
Burnup Chart
Risks
Links to Project Risks in Trello Link to Risk Chart
Sprint Planning
- We planned the following issues in sprint planning today Link to Issues in Jira (Cached Image)
Our goals for the sprint are:
- Design view of licences - PPLs
- User research - requirements for other kinds of PPL
- “My tasks” list - working software
- pdf export of PPLs
Screenshots of the PPL application prototype
Google Analytics for this report
This shows:
- total number of users
- number of new users