Summary as of 9th May 2018

What’s Blocking us / Issues

  • The data exporting functionality in ASPeL cannot be used reliably. Suppliers have said they will not give us access to their database. We need a way to access the underlying data from ASPeL to import it into our systems for private beta.

Just Done

  • Validating of user journeys with licencing staff
  • Created backlog of user stories for private beta mapped to identified user needs
  • Finished establishment landing page and licensed premises page for beta

About to Do/Doing

  • User Research with Inspectors using new prototypes
  • Development of the Establishment details page for establishment users for beta
  • Development of the user feedback page for use in beta

Things to be aware of

  • The team will most likely move back into Lunar house at the beginning of June

Click here for our High-Level Road map

Link to Live Road map in Trello (Cached Image)

Click here for metrics / progress against plan

Week 2 - Sprint 7 - Release 1

Risks

Links to Project Risks in Trello (Cached Image)

Risk Management Chart

Sprint Planning

We planned the following issues in sprint planning today Link to Issues in Jira (Cached Image) Our two goals for the sprint are

  • Develop everything for the establishment facing view for private beta (except named people)
  • Continue establishment licence amendments user research

Output from User Research

A Week in the Life of an Inspector