Done

  • Schedule and hold session with enforcement manager/admin - user research
  • Initial exploration into non-compliance flags - design
  • Fixed issue with draft additional availability amendments appearing incorrectly - working software
  • Improved styling of link filters - working software
  • Added new options of other mammals and other carnivores to ROPs - working software
  • Added progress indicators to ROPs setup journey - working software

About to Do/Doing

  • Plan testing of compliance flags designs with inspectors and enforcement team - user research
  • Creating user journey maps and then prototypes of non-compliance flag journeys - design
  • Add support for edit and resubmit of a category E PIL application - working software
  • Add notifications for RA task events - working software
  • Add support for internal deadlines/targets to application and amendment submissions - working software

Bugs Fixed this week

The following bugs were fixed this week. Bug Fixes week to Wednesday 08 December 2021

We planned the following issues in this sprint Sprint 99

Support tickets and known issues

Link to Support Board

Support board - cached

Click here for metrics / progress against plan

Sprint 99

Post Release Roadmap

These are the goals for the current sprint

  1. Initial designs for compliance - design flags
  2. Internal target reporting - working software
  3. Plan testing for compliance flags designs - user research

These were the goals for the previous sprint

  1. Make changes to PPL application submission process release candidate [On hold]
  2. Explore compliance flags - user research and design [Done]