Summary as of 8th August 2018

What’s Blocking us / Issues

  • Contract renewal for the existing system has still not been signed off

Just Done

  • Demonstrated working software for creation of new user accounts
  • Demonstrated Initial designs for PIL application
  • Conducted user research with members of the licensing team on approval PEL amendments

About to Do/Doing

  • Continuing design work on PIL applications in preparation for User Research
  • Produce designs for PEL amendments for named people in preparation for User Research
  • Develop working software for end-to-end creation of user accounts

Things to be aware of

  • A new software developer joined the team this week, another new software developer will join the team next week
  • Marvell Consulting have a new office space in London Bridge which the team will work from on occasion (specifically to help ease the burden of SC clearance). Members of the team will continue to also work in Lunar house and occupy our bank of desks on the 18th floor
  • We are also interviewing for a new designer to replace the designer who is leaving the team

Click here for our High-Level Road map

Link to Live Road map in Trello (Cached Image)

Click here for metrics / progress against plan

Week 1 - Sprint 14 - Release 1

Burn Up Chart

HTML5 Icon

Risks

Links to Project Risks in Trello (Cached Image)

Risk Management Chart

Progress against previous Sprint Goals

  • Goal - “Create User” - end-to-end journey in working software: This goal was not achieved “end-to-end” because of a critical bug encountered in the database access layer. We have adopted a different approach which should also help with database migrations. We aim to complete Create User in this sprint
  • Goal - Get designs ready for User Research on PILs: This goal was intended to stretch across two sprints and in continuing in this sprint
  • Goal - Test PEL amendment journeys with licensing team, so ready for development: Completed

Sprint Planning

We planned the following issues in sprint planning today Link to Issues in Jira (Cached Image)

Goals for the sprint are

  • Complete the “Create User” journey, end-to-end as working software
  • Get PIL application and Profiles designs ready for User Research

Sample Design Prototypes

Some screenshots from the prototypes that we tested with licensing officers for approval of PEL amendments.

HTML5 Icon
HTML5 Icon