Summary as of 7th August 2019
Sprint 39
Just Done
- Design - Category E PILS
- Merge and deduplication of profiles - working software
- Design - activate a Revoked project license
About to Do/Doing
- Support search by licence number for ASRU users for internal and profile search
- Make task labels unique in task lists - working software
- User research review PPL application with inspectors
- Design - Print view of PEL
- Design - Print view of PIL
Bugs Fixed this week
The following bugs were fixed this week. Bug Fixes w/c 31/07/2019
Support tickets and known issues
Things to be aware of
- 4 Establishments are now live using the new Aspel system
- We expect 17 further establishments to go live with the new system next week
Click here for metrics / progress against plan
Week 1 - Sprint 39 - Release 1
Sprint Planning
- We planned the following issues in sprint planning Link to Issues in Jira (Cached Image)
Our goals for the sprint are:
- Continue roll-out to 2nd cohort of establishments
- Address critical errors in timely fashion