Summary as of 7th February 2018

What is Blocking Us / Issues

  • Access to the building is still a substantial blocker - this is the sixth week that this has been a problem. Marvell-Consulting have managed to arrange alternative temporary accommodation, but it is not ideal. A security waiver for Lunar house is not possible

Just Done

  • Research plan approved Tuesday 6th Feb
  • Agreed sample of users to contact for the next three iterations of research engagement
  • Established KPI’s and begun baseline measurements
  • Gathered establishment licence statistics from ASPEL which will inform profiles for user research
  • Completed content audit for gov.uk ASL
  • Team members were introduced to the Home Office research and design community in a meetup
  • The team met with a cross-government licensing team at GDS to understand commonalities
  • Captured actions arising from last week’s governance meeting
  • Team members met with service standards team to discuss the way we plan to assess our service

About to Do/Doing

  • Today we will plan our activities for the next two weeks in sprint planning.
  • The main activities that will be planned will be the research and design prototype activities that have been outlined in the approved research plan
  • This will likely focus initially on viewing the establishment licence

Things to be aware of

  • Mick Carling will not be working with us after the end of the week
  • Project risks have been moved from Jira to Trello (both are issue tracking systems)

Click here for our High-Level Roadmap

Link to Live Roadmap in Trello (Cached Image)

Click here for metrics / progress against plan

Week 6 - Release 0

Link to Issues in Jira

Risks

Links to Project Risks in Trello (Cached Image)

Sprint planning

  • We planned the following issues in sprint planning today Link to Issues in Jira (Cached Image)
  • Our two goals for the sprint are
    1. “Create designs to test with users using realistic dummy data”
    2. “Front-end connected to mock data”