Summary as of 5th December 2018
Sprint 22 - Mid Sprint
Just Done
- User Research - Shared findings from PPL testing at LASA and ASRU
- User Research and Design - Reviewed PPL application for next round of testing
- Working software - Wrote business logic to query task service for task lists for different types of user
- Working software - Built user permissions admin screens
- Working software - Fixed a number of bugs with user onboarding
About to Do/Doing
- Designing the next PPL application iteration
- Planning further research in January
- Working software - development of PPL application prototype
Things to be aware of
- Members of the team have a meeting arranged for next week with the Cyber Security Operations Centre (CSOC)
Click here for our High-Level Road map
Link to Live Road map in Trello (Cached Image)
Click here for metrics / progress against plan
Week 2 - Sprint 22 - Release 1
Burnup Chart
Risks
Links to Project Risks in Trello (Cached Image)
Sprint Planning
- We planned the following issues in sprint planning Link to Issues in Jira (Cached Image)
Our goals for the sprint are:
- Content Design - Full PPL Research Application
- UR - Playback findings from LASA and ASRU
- Build PPL Prototype
“University of Croydon” Test Environment
Screenshots
Need a test account?
If you need a test account please contact animalscience@digital.homeoffice.gov.uk