Summary as of 5th January 2018
What is Blocking Us
- Access to the building is still an issue for some (3) members of the team
- Procurement necessary items for the group e.g. stationery, electrical has yet to be finalised
Just Done
- Git/Github repositories created
- Agile meetings (stand-up, show and tell, retrospective, planning) arranged
- Agreed roles and responsibilities
- Reviewed the outputs from discovery
- Conducted user research with inspectors and policy
- Documented outputs of user research
- Planned and arranged user research for next week and the following week
About to Do/Doing
- Next week we will be conducting user research in Edinburgh and Birmingham
Things to be aware of
Click here for our High-Level Roadmap
Week 1 - Release 0
Click here for metrics
Week 1 - Release 0