Summary as of 3rd July 2019
Sprint 36 - Mid Sprint
Just Done
- Digital views of the granted licence
- PPL file uploads design
- Working software MVP secondary availabiilty
About to Do/Doing
- Preparation for the HOLTIF meeting
- Iterations for the Print views of the Granted Licences
- Project landing page design updates
Things to be aware of
- We continue to work to acheive authority to operate
Click here for Prioritised Road Map
Click here for metrics / progress against plan
Week 2 - Sprint 36 - Release 1
Burnup Chart
Risks
Links to Project Risks in Trello Link to Risk Chart
Sprint Planning
- We planned the following issues in sprint planning Link to Issues in Jira (Cached Image)
Our goals for the sprint are:
- Complete Inspector Roadshow
- Prepare for HOLTIF meeting
- Print view PPL granted licence
- ATO
- PPL discard project amendments - design
- Category E Pils - (Design Only)