Summary as of Wednesday 01 December 2021

Sprint 98 (Emu)

By William Warby - Flickr, CC BY 2.0, https://commons.wikimedia.org/w/index.php?curid=19785663

Just Done

  • Held research session with inspectors to explore non-compliance flags in ASpeL - user research
  • Defined management metrics for managing tasks - design
  • Initial kick-off for exploring compliance cases - design
  • Added pages to report the number of tasks assigned to ASRU users - working software
  • Added download timestamps to licence documents - working software
  • Added PPL continuation data to PPL application report - working software

About to Do/Doing

  • Visualising how management metrics will be displayed in ASPeL - design
  • Developing user journeys for adding compliance flags - design
  • Updates to content of PPL expiry warning notices - working software
  • Adding progress indicators to ROPs setup journey - working software
  • Changes to the PPL applications process - working software

Bugs Fixed this week

The following bugs were fixed this week. Bug Fixes week to Wednesday 01 December 2021

We planned the following issues in this sprint Sprint 98

Support tickets and known issues

Link to Support Board

Support board - cached

Click here for metrics / progress against plan

Sprint 98

Post Release Roadmap

  1. Make changes to PPL application submission process release candidate [On Hold]
  2. Explore compliance flags - user research and design [In Progress]