Summary as of Wednesday 01 September 2021

Sprint 92 (Yak)

Yak

Weekly summary

We demonstrated the working ROPs software to several people in ASRU knowledgeable about the ROPs process.

We continue to address further issues and changes regarding ROPs.

Just Done

  • Refinements to PPL assessment designs based on Ops team feedback - design
  • Minor updates to RoPs - design
  • Draft designs to make it easier for inspectors to preview the PPL licence before granting - design

About to Do/Doing

  • General improvements including previewing licences, editing conditions and highlighting overdue RAs - design
  • Looking into a request to add a new question to PPL applications re: transferring animals between different sites within large establishments - design
  • Improving task list filtering options for internal users - working software
  • Make the process for change of PPL holder require the same endorsements as PPL amendments - working software

Bugs Fixed this week

The following bugs were fixed this week. Bug Fixes week to Wednesday 01 September 2021

We planned the following issues in this sprint Sprint 92

Support tickets and known issues

Link to Support Board

Support board - cached

Click here for metrics / progress against plan

Sprint 92

This is our goal for the current sprint (Yak)

  1. Continue to address ROPs issues

These were our goals for the previous sprints (Xenopus)

  1. Complete outstanding ROPs issues
  2. Review role descriptions for ASRU users

Sample Design Prototypes

Refinements to PPL assessment designs based on Ops team feedback

HTML5 Icon

Google Analytics for this report

Google Analytics