Summary as of 1st August 2018
Sprint 13 - Mid Sprint
What’s Blocking us / Issues
- We are still waiting for final sign-off on contract renewal for the current system
Just Done
- User research carried out with licensing team on inbox and workflow for amendments to establishment premises
- Produced design ideas for user account creation, account permissions and PIL application
- Built database migration system
About to Do/Doing
- Continue to prepare prototype designs for User Research with PILs
- Design workflows for the addition/amendment of named people on licences
- Develop working software for user on-boarding journeys
Things to be aware of
- Sadly one of our designers will be leaving the team on 22nd August
- Two new developers will be joining the team (one will start Monday 6th, the other Monday 13th)
- The overall risk score (see link below) has reduced. The addition of new developers to the team is viewed as reducing the likelihood that we will not be able to turn off the existing system in August 2019
Click here for our High-Level Road map
Link to Live Road map in Trello (Cached Image)
Click here for metrics / progress against plan
Week 2 - Sprint 13 - Release 1
Risks
Links to Project Risks in Trello (Cached Image)
Burn up Chart
A new addition to the weekly report. This shows work currently completed against all of the work which is required to be delivered by August 2019.The dotted lines are predictions of how the amount of work will change, and likely progress.
Sprint Planning
- We planned the following issues in sprint planning last week Link to Issues in Jira (Cached Image)
Sprint Goals
- “Create User” - end-to-end journey in working software
- Get designs ready for User Research on PILs
- Test PEL amendment journeys with licensing team, so ready for development